Operational Excellence Programme


OTC Site - Pragmatism;

  • Business analysis – Site Master plan Pharma OTC site (Switzerland / 10 Year Plan); concept, Business analysis and approval, Excellence Programme. Cost, Quality and Schedule driven by business evolution opportunities. Included cut and carve upgrades, whilst maintaining ongoing production
  • Site recognised as best in class by business

Pharma Site - Innovation;

  • Reduced time to market – Pharma API Investment (UK / TIC £83 mio); Introduction of LEAN techniques by integration of engineering, construction, commissioning and start up, reducing the project schedule from 26 to 17 months (concept to Start up first batch)